A last-time buy arrives as a deadline rather than a project. A supplier announces an end-of-life date, a final order date follows, and a programme manager has a few weeks to decide how many modules to take. The number chosen then is a commitment: there is no second order, and every unit bought has to be stored, insured and eventually used or written off.

This guide treats the quantity as a service-level decision rather than a forecast, builds it from demand, lead time and scrap, and puts the costs on the other side of the ledger: shelf life, pallet positions, re-qualification, and the break-even against a redesign. It also covers where the stock should sit and how the number can be revised when demand falls.

An LTB quantity is a service level, not a forecast

An LTB quantity answers a question about probability: how likely is it that this stock lasts to the end of production? A forecast answers a different question, the most likely demand, and buying exactly the forecast leaves roughly a fifty percent chance of running short before the programme ends. That is why a buffer sized from a forecast feels adequate in the meeting and turns out to be short in the third year.

Set the quantity at a percentile and price both tails. Buying to a high percentile costs more stock and creates a write-off risk; buying lower protects cash and accepts a shortage risk. Which is right depends on what a line stop costs against what an unused pallet costs, and both figures are knowable before the order. The commercial side of that conversation sits in the custom sourcing guide, and the strategic case in how a last-time buy protects a supply chain from end-of-life disruption.

Sizing the buffer from demand, lead time and scrap

The quantity has four inputs and one subtraction. Remaining demand is what the programme consumes from the last delivery to end of production, including service and spares. The lead time term covers the gap between final order and final delivery, during which the line still runs. Scrap covers handling losses and yield at your own assembly step, and the subtraction is the stock already on hand or in transit.

LTB quantity = (remaining demand + demand during final lead time) x service factor / (1 - scrap rate) - stock on hand

Work an illustrative case with your own numbers rather than a supplier's. If the remaining build needs a known quantity and scrap runs at a low single-digit percentage, the service factor is where judgement sits: above one adds margin for forecast error, one is a coin toss. Apply the same arithmetic to spares, since aftermarket demand often outlives the production line.

7.0 inch 800x480 TFT LCD display with capacitive touch panel
A 7.0 inch 800x480 TFT LCD display with capacitive touch panel. A bonded touch panel is the element that most often forces a storage decision, because the adhesive and the controller are harder to replace than the glass.

What shelf life does a stored module actually have

There is no generic answer, which is precisely why the number has to be requested in writing for each part number. Storage life depends on the materials in the stack: polariser adhesive, the elastomer or solder connection to the driver, the plating on the connector, the tapes and the light guide. Temperature and humidity dominate all of them, and a sealed barrier bag with desiccant changes the answer again.

The mechanisms are slow and cumulative. Adhesive layers lose tack and can delaminate at the edge; connector plating oxidises and raises contact resistance; a light guide can yellow; a driver IC in a humid package can absorb moisture and crack during reflow if it is ever reworked. Ask the supplier for the stated storage life, the conditions it assumes, and whether the figure survives a broken seal, then write the answer into the storage procedure. Conditions themselves can be defined against published standards such as those in the ISO catalogue.

What a pallet position costs over five years

Space, capital, insurance and write-off, per unit per year.

The space charge dominates because a rented pallet position looks free once the warehouse is already paid for, and the write-off provision grows with every year the buffer sits.

Buffer stock is inventory with a clock on it, and the clock is charged whether or not the units are used. Four costs accumulate: the space a pallet position occupies, the capital tied up in the units, insurance and stock-count labour, and the reserve for units that will never be consumed.

Convert everything to a cost per unit held per year, then multiply by the years the buffer will sit. A position that holds a known number of modules and costs a monthly rate per position produces a per-unit annual figure once you divide; add the cost of capital at your own internal rate, and a write-off provision for the fraction expected to remain at end of production. The result often exceeds the discount gained by buying the whole quantity at once.

Re-qualification cost when the buffer is drawn down slowly

A buffer drawn down over five years keeps a part number technically active long after the supplier has moved on. That has a cost that rarely appears in the LTB calculation: the evidence supporting the part has an expiry of its own. Declarations, test reports and process controls were written for a production line that no longer runs the part.

Practical exposure comes in three forms. Sample-based re-verification at intervals costs engineering time and a test slot. Any change in the supplier's process, even one made for other customers, may never have been communicated, which is why the change-notification discipline automotive programmes run under AIAG expectations matters here. And a substance restriction or declaration revision can make old stock harder to place on a regulated market, which is where the RoHS Directive 2011/65/EU documentation for a stored batch matters as much as for a new one. Budget a re-verification allowance per year of storage rather than assuming the original qualification covers the whole buffer.

Storing on site, in bond or at the supplier

Where the buffer sits changes the cost, the control and the risk. On site, the stock is visible and available, and it consumes space you may need for production. A bonded warehouse defers duty until the goods are released. Holding stock at the supplier or in a consignment arrangement keeps it off your books and your floor, but it depends on the supplier still existing and still being willing to ship.

OptionControl and accessMain cost driverMain risk
On siteImmediate, fully visibleSpace and handlingDamage and inventory drift
Bonded warehouseGood, with customs formalitiesStorage plus duty timingRelease delays and paperwork
Supplier heldIndirect, by agreementStorage fee or price upliftSupplier exit or priority loss

Whichever route is chosen, the agreement should say who owns the stock, who insures it, how it is packed for long storage, and what notice applies before the arrangement ends. For a bonded option, the tariff position follows the HS nomenclature and duty rates are published through services such as the EU Access2Markets.

Revising the quantity when demand falls after the order

The LTB order is placed against a demand curve that can move, and it usually moves down. Nothing about that is unusual: programmes are cancelled, volumes are cut, and a product meant to run four more years stops in two. The question is whether the order was written so the quantity can change, or whether it locked a number the business later has to write off.

Negotiate the revision mechanism at the same time as the quantity. A delivery schedule with staged call-offs on your existing Incoterms 2020 terms, a cancellation window expressed in weeks, and a tolerance band around the committed total all convert a fixed bet into a managed one. Where the supplier will not accept a cancellation, ask for a price step at defined volumes instead, or for the right to assign unused stock to another programme. Record the mechanism in the purchase order, because a verbal understanding about flexibility does not survive a change of account manager.

3.5 inch 320x240 IPS TFT LCD display with resistive touch panel
A 3.5 inch 320x240 IPS TFT LCD display with resistive touch panel. Smaller modules are easier to store in quantity, but the tray and bag still have to survive years of handling.

Moisture, ESD and connector plating in long storage

Long storage is a slow environmental test, and most of the failures it produces are preventable at the packing stage. Moisture is the first: a module stored in a sealed bag with desiccant holds its condition, while one in a carton on a rack absorbs humidity with every season. Electrostatic discharge is the second, because a bag opened and closed repeatedly loses the protection it was designed to give.

Set the storage conditions as a written instruction: bag and desiccant intact, humidity indicator visible and within its limit, racking off the floor, temperature stable and recorded. Handle only at an ESD workstation once the seal is broken. Connector plating is the third item: contacts oxidise over years, so inspect a sample at intervals rather than trusting the seal. Record the storage start date on every carton and run first-in, first-out, because a buffer without dates becomes a pile nobody can plan against. These conditions belong in the reliability record too, as the CDTech quality and reliability guide sets out.

The break-even line between an LTB and a redesign

An LTB competes with a redesign, and the comparison is often made badly because the two sides are counted differently. The buy side includes the purchase, the years of storage, the re-qualification allowance and the write-off risk. The redesign side includes engineering time, tooling, firmware, qualification testing, any certification impact, and the schedule exposure of a new part arriving late.

Put both on a per-year-of-remaining-production basis and the line becomes visible. A short remaining life with a modest buffer usually favours the buy, because redesign cost is spread over few units. A long remaining life, or a buffer large enough to need a second warehouse, usually favours the redesign even at a higher unit price. In between, a smaller buffer plus a redesign started in parallel is often cheapest.

Next step. If your team is sizing a buffer for a display going end of life, CDTech can put the storage, packing and last-time-buy terms behind the numbers in front of you. The frequently asked questions cover the common cases first.

Ask about last-time-buy planning · [email protected]

FAQ

What shelf life do LCD modules have?

There is no single figure, because storage life depends on the polariser adhesive, connector plating, tapes and light guide, and on the temperature and humidity of the store. Ask the supplier to state the life in writing for the specific part number, with the conditions it assumes, and ask whether the figure survives an opened seal. Then write those conditions into the storage procedure and record the storage start date on every carton.

Is a last-time-buy cheaper than a redesign?

It depends on how much production remains. A buy usually wins when the remaining life is short, because redesign cost is spread over few units and the schedule risk is avoided. A redesign usually wins when the remaining life is long, or when the buffer is large enough to need extra space for years. Put both sides on a per-year basis, include storage and re-qualification in the buy side, and start the redesign in parallel if the answer is genuinely close.

Where should buffer stock be stored?

On site for access and visibility, in a bonded warehouse when duty deferral matters for a large consignment, or at the supplier under a consignment or hold arrangement when floor space is the constraint. Each has a different risk: damage and inventory drift on site, release paperwork in bond, and supplier exit for held stock. The agreement should name the owner, the insurer, the packing standard and the notice period before the arrangement ends.

How is an LTB quantity revised if demand drops?

Through a mechanism negotiated before the order, not after the drop. Staged call-offs, a cancellation window in weeks, a tolerance band around the committed total, or a price step at defined volumes all convert a fixed commitment into a managed one. Where the supplier refuses flexibility, ask for the right to assign unused stock to another programme. Put the mechanism in the purchase order, since an informal understanding rarely survives a change of contact.

×