A custom display programme usually runs through three or four sample stages, and each one exists to answer a specific question. Programmes that treat the stages as deliveries rather than as decisions tend to repeat work, and programmes that skip a stage discover the same information later at higher cost. Knowing what each stage proves is what makes the schedule predictable.
Last updated:
Each stage closes a different uncertainty.
| Stage | Question answered | Typical content |
|---|---|---|
| Evaluation sample | Does the concept function and fit? | Standard module, approximate mechanics, working interface |
| A-sample | Does the design work with the intended materials and format? | Custom front, first mechanical design, functional interface |
| B-sample | Does it meet the environmental and optical requirements? | Production-intent materials, bonding, coatings |
| Production sample | Can the line build it consistently? | Production tooling, process parameters, inspection standard |
The distinctions matter commercially: an evaluation sample validates an idea cheaply, while a production sample validates a process expensively. Asking for production-level confidence from an evaluation sample is the most common way to spend money early and learn nothing.
A short list, applied every time.
Recording the results with photographs and measurements, rather than reporting impressions, is what makes the next stage faster. The evaluation should also record what was not tested, so that the outstanding questions are visible rather than assumed.
Cost rises with production intent.
Evaluation samples often use standard parts and can be inexpensive. A-samples introduce custom front tooling and hand assembly. B-samples use production-intent materials and processes, including bonding and coating, and carry process setup cost. Production samples use the actual tooling and process, and their cost is largely the setup and yield of that build. Where a programme wants to compress the schedule by skipping a stage, the saving is usually smaller than the cost of discovering the same issue during a production build.
The practical approach is to decide at the outset which stages are necessary for the product’s risk profile, and to state that decision in the programme plan with the reasons recorded. Workmanship expectations for the assemblies produced at each stage are published by bodies such as IPC, and environmental test capability by chamber suppliers such as Thermotron.
Two variables dominate: tooling and material availability.
A sample schedule is driven by the tooling lead time for any custom items and by the availability of the panel and materials. Where the design uses a standard panel and a custom front, the schedule is relatively short. Where a panel-level customisation is involved, the lead time extends to the panel maker’s own cycle. The programme’s most reliable control is to freeze the specification before tooling and to obtain the supplier’s assumptions about material lead time in writing.
Asking for an accelerated sample is possible when the constraint is production scheduling, and much less possible when it is a tooling or material lead time.
A payment gate is only useful if it releases against a named deliverable and an inspection you can actually perform, otherwise it becomes a schedule milestone that transfers cash without transferring risk. The table links each stage to what arrives and what to check before paying.
The list is a programme-control model, not a price list: amounts, stage names and what counts as acceptance depend on the project and on the supplier’s own process. What transfers between projects is the structure — money moving against artefacts, with an inspection between the two.
| Stage | Deliverable | What the gate normally releases | What to inspect before releasing it |
|---|---|---|---|
| Specification baseline agreed | Controlled specification + mechanical drawing | Engineering deposit | Drawing checked against the enclosure and connector space |
| A-sample (form and fit) | A-sample units + test report | Sample payment | Active area, thickness, FPC exit, connector and mounting hole positions |
| B-sample (production intent) | B-sample + optical/electrical data | Tooling payment | Gamma, white point, brightness, uniformity and touch performance on the exact stack |
| Golden sample approval | Signed golden sample + final drawings | Pre-production payment | Change-control levels agreed and recorded |
| Pilot / PVT | Pilot report + first-article inspection | Balance per schedule | Process capability and traceability records, not only passing units |
Two failure patterns recur. Paying tooling before the B-sample optics are confirmed moves the risk of a stack change onto the buyer, because the tooling is already cut for the earlier geometry. And accepting a golden sample without recording the change-control level leaves the first production batch free to drift within “normal” tolerances that were never written down.
What to ask for as evidence. Request a stage plan with deliverables and acceptance criteria, the inspection report formats used at each gate, the change-control levels that apply after golden-sample approval, and the document set you will receive at handover. The quality assurance and factory compliance page lists the records that should accompany each stage.
Attach payments to outcomes, not dates.
Attaching the tooling payment to drawing release is the most useful gate, because the drawings are what the buyer can review and approve before money is committed. CDTech’s notes on the sample process and tooling describe the deliverables to expect at each point.
Five patterns, all recognisable.
Each of these has a low-cost prevention: freeze the specification, state the environment early, agree the acceptance standard, confirm the host interface, and state the volume. The prevention is cheaper than the stage repeat in every case.
What to have in hand before moving on.
| Gate | Before proceeding |
|---|---|
| Evaluation to A-sample | Concept validated; envelope and interface confirmed; volume band agreed |
| A-sample to B-sample | Mechanical design frozen; optical acceptance standard agreed; material list defined |
| B-sample to production sample | Environmental tests passed; bonding and coating processes defined |
| Production sample to release | Process capability shown; inspection standard with boundary samples signed; documentation package complete |
Moving through these gates in order, with the evidence recorded at each, is what makes the final stage a confirmation rather than a surprise. Where a programme has to compress, it is usually better to compress the time spent at each gate than to remove a gate altogether.
Information flows both ways.
Suppliers can only meet a schedule if they know which requirements are genuinely fixed and which are preferences. Telling the supplier that the enclosure is fixed but the coating is negotiable, for example, allows them to choose a coating that is available immediately. The same principle applies to the acceptance standards: sharing the boundary samples and the way they were established helps the supplier match them rather than guess.
A programme review after each stage – short, with the evidence in front of both parties – is the mechanism that keeps the schedule and the expectations aligned.
An A-sample demonstrates that the design works with the intended format and mechanics; a B-sample demonstrates that it meets the environmental and optical requirements using production-intent materials and processes such as bonding and coating. Skipping the B-sample usually means discovering material issues during the production build.
It depends on tooling and material availability: a standard panel with a custom front is relatively quick, while panel-level customisation follows the panel maker’s own cycle. Obtain the supplier’s material lead-time assumptions in writing, and freeze the specification before tooling is released.
Attach the tooling payment to the release of the drawings, which the buyer can review and approve, rather than to a project start date. Subsequent payments should be attached to sample shipment, sample approval and delivery, so each gate has a defined deliverable.
Mechanical fit against the drawing, optical performance in the intended lighting, interface and timing with the actual host, touch behaviour with the gloves in use, front appearance against the boundary samples, and assembly as a service technician would perform it. Record measurements and photographs, and note what was not tested.
Send the customisation scope, required stages and target dates to CDTech; the reply will set out the stage plan, the deliverables at each gate and the schedule drivers for the specific design.
Contact [email protected] or use the contact page.
By continuing to use the site you agree to our privacy policy Terms and Conditions.